How to price a construction job
A construction bid price is built up in layers:
- Direct costs – materials (with sales tax and waste), labor including burden, equipment, subcontractors, permits and job-site costs.
- Overhead – the cost of running the business that is not tied to one job: office, vehicles, insurance, accounting, software and your own unbilled time. It is usually added as a percentage of direct cost.
- Contingency – a cushion for things you cannot see yet, such as rot behind a wall or a price rise on lumber.
- Profit – what the business earns for taking the risk, added as a markup.
Bid price = (direct cost + overhead + contingency) × (1 + profit %)
Worked example
A 450 sq ft remodel has $12,000 of materials plus 7% sales tax ($840), 220 labor hours at $38 ($8,360) plus 30% burden ($2,508), $900 of equipment, $6,500 of subcontractors and $1,200 of permits and job costs – a direct cost of $32,308. Adding 12% overhead ($3,876.96), 7% contingency ($2,532.95) and a 10% profit markup ($3,871.79) gives a bid price of $42,589.70, or about $94.64 per square foot.
What is labor burden?
Labor burden is everything an employee costs you on top of their wage: the employer's share of Social Security and Medicare (7.65%), federal and state unemployment tax, workers' compensation insurance – which is high for construction trades – general liability tied to payroll, and any health insurance, retirement or paid time off. For construction crews it typically adds 25–40% to the hourly wage. Forgetting it is one of the most common reasons small contractors underbid.
Typical overhead and profit for contractors
| Item | Common range |
|---|---|
| Overhead | 10–20% of direct cost |
| Profit | 5–15% markup |
| Contingency (new work) | 5–10% |
| Contingency (remodels) | 10–20% |
| Materials waste factor | 5–15% depending on material |
Your own numbers are what matter: divide last year's overhead costs by last year's direct job costs to find your real overhead percentage.
Markup vs margin
A markup is a percentage of cost; a margin is a percentage of the selling price. A 25% markup on cost is a 20% margin. The calculator shows both so you can check that the price covers what you need. Compare other figures with the markup calculator and the profit margin calculator.
From estimate to invoice
Once you have the price, write it up with the construction estimate generator, convert it to an invoice when the client accepts, and bill progress payments with the construction invoice template.
For planning only. Costs vary widely by region, trade and season – always use current supplier and subcontractor quotes.
Frequently asked questions
How do contractors calculate a bid?
Add up direct costs (materials with tax, labor with burden, equipment, subcontractors and permits), add overhead as a percentage, add contingency for unknowns, then apply a profit markup. The calculator does each step.
What is a good profit margin for a contractor?
Many residential contractors aim for a gross margin (overhead plus profit) of about 20–35% and a net profit of about 5–15%, but it depends on the trade, job size and risk.
Should contingency be shown to the client?
It can be either. Some contractors show it as a separate line that is only used with the client's approval; others build it into the price. Be consistent with what your contract says.
How do I calculate cost per square foot?
Divide the total bid price by the project area. Use it to compare with similar jobs, but price each job from its actual quantities rather than from a per-square-foot figure.